Project 02 |

Design three (3) floated bridges on seawater. Two of them connected Sinai with Ismailia, while other in shat area near to Suez canal

Structure system type:

  • Slabs on caisson bored piles

Programs used:

  • SAFE2016 ≫ Modelling, analysis and design concrete bridge Slabs and retaining wall.

  • Specific geotechnical programs≫ modelling, analysis the soil structure as well as design concrete piles under gravity and lateral force

  • AUTOCAD 2019 ≫ Detailed structural drawings

  • PROKON≫ Check on crack width

  • Microsoft Word 2017 ≫ Making detailed calculation note

Challenges: ​

  • Achieve pile axial capacity design due to gravity loads

  • Achieve pile lateral capacity design due to wind and earthquack loads

  • Design rotational pile against wind loads

  • Berth front slope configuration to be suitable for the floating bridge under all water levels.